The buyer owns the user requirement specification (URS), the qualification plan and the approval of every protocol and report; the supplier provides the functional and design specifications, drawings, certificates, FAT and SAT documentation, and usually drafts IQ and OQ protocols for the buyer to approve and execute. PQ is the buyer's responsibility with supplier support. Agree the full document list, formats and approvals in the purchase order, since documents are often what delays qualification.
The document pack and owners
| Document | Owner | Supplier role |
|---|---|---|
| User requirement specification (URS) | Buyer | Review and confirm compliance |
| Functional and design specifications | Supplier | Write; buyer approves |
| Risk assessment | Buyer (with supplier input) | Provide design risk analysis |
| Design qualification (DQ) | Buyer | Provide design evidence and traceability to URS |
| Drawings, P&IDs, electrical schematics | Supplier | As-built versions at handover |
| Material and surface finish certificates | Supplier | Traceable to parts |
| Calibration certificates | Supplier | For all critical instruments |
| Software documentation | Supplier | Functional specification, configuration, Part 11 and GAMP assessment |
| FAT protocol and report | Supplier | Execute at factory; buyer witnesses and approves |
| SAT protocol and report | Supplier or buyer | Execute on site |
| IQ and OQ protocols and reports | Buyer | Supplier often drafts and supports execution |
| PQ protocol and report | Buyer | Technical support |
| Manuals, spare parts list, SOP inputs | Supplier | Operation, maintenance and cleaning manuals |
| Training records | Supplier and buyer | Deliver and record training |
Regulatory basis
EU GMP Annex 15 (2015) sets the sequence: specifications in a URS as the point of reference, then DQ to demonstrate GMP compliance of the design, then FAT and SAT where appropriate, then IQ, OQ and PQ. It allows IQ and OQ to be combined and allows FAT results to be reused in IQ and OQ where justified, which is why supplier test quality matters. The ISPE commissioning and qualification guide and ASTM E2500 follow a similar science- and risk-based approach.
Contract tips
- List every document, its format, language and number of copies in the purchase order.
- Agree templates or approve the supplier's templates early.
- Tie payment milestones to document delivery and approval, not just shipment.
- Require as-built drawings and final software versions at handover.
- Specify electronic delivery in searchable formats.
See FAT and SAT and the plant qualification checklist.
Companies listed in the Hello Pharma supplier directory
The Hello Pharma supplier directory lists 33 companies relevant to this guide, grouped below by machine type or category. Each name links to the company's directory entry, with a description, technologies, location and website. Companies confirmed against their websites or public listings appear first in each group.
Inclusion is not an endorsement or ranking. Many categories are inferred from company names and segments, so confirm capabilities, approvals and service reach directly with each supplier. Search all 1,232 companies.
Validation services (13)
Airtech Systems India Pvt. Ltd.; Bliss-ca Technologies; D.D. Enterprises; Salesworth Synergies LLP; Thermolab Scientific Equipments Pvt Ltd; Autocal Solutions Pvt. Ltd.; Hyde Engineering + Consulting; June Enterprises Pvt Ltd.; Metina Pharmconsulting Private Limited; Pratham Technologies Pvt. Ltd.; Sergusa Solutions Pvt. Ltd.; SpectrumPharmaTECH Consultants Pvt. Ltd.; TechnoValue Solutions Pvt Ltd.
Open the full entries: Engineering and validation services list filtered to validation services · Lab and analytical list filtered to validation services · Packaging machinery list filtered to validation services · Cleanroom, HVAC and containment list filtered to validation services
Engineering services (24)
D.D. Enterprises; Fabtech Technologies International Ltd.; Anvay Pharma Systems Pvt. Ltd.; Aspire India; Bio Pharm Engineering; Camfield Engineers; Centech Engineers Pvt. Ltd.; EMCO Engineering; Hexagon Product Development Pvt. Ltd.; Hyde Engineering + Consulting; Landsky Engineers Pvt. Ltd.; M K Teknology 1 Pvt. Ltd.; MRC Systems FZE; Orbit Technologies Pvt. Ltd.; Parth Engineers & Consultant; Pharmatech Engineering Company; Pharmintech Turnkey Solutions Pvt Ltd; Pratham Technologies Pvt. Ltd.; Rihim Pharma Consultancy Pvt. Ltd.; Skytech Systems (India) Pvt.Ltd.; SMMS Engineering Systems Pvt. Ltd.; SpectrumPharmaTECH Consultants Pvt. Ltd.; SRJ Engineers Pvt. Ltd.; Vishva Protech Pvt. Ltd..
Open the full entries: Engineering and validation services list filtered to engineering services
Frequently asked questions
Who writes the URS?
The buyer. It defines what the equipment must do and is the reference point for the whole qualification.
Who executes IQ and OQ?
The buyer is responsible, but suppliers often draft protocols and help execute them. The buyer's quality unit approves.
Can FAT results replace IQ and OQ tests?
EU GMP Annex 15 allows FAT tests to be reused where assessed and justified, avoiding repetition if conditions did not change.
Is PQ the supplier's job?
No. PQ shows the equipment performs consistently with your product and process, so it is the buyer's responsibility.
Related guides
Sources
- EU GMP Annex 15 qualification and validation, European Commission
- New EU GMP Annex 15 revision valid from 1 October 2015, ECA Academy
- Q&A: user requirements specifications and C&Q, ISPE
- Qualification vs validation, GMP Insiders
This guide is general information to support decisions and is not engineering, validation or regulatory advice for a specific project.